System performance <80% → 110% of the intended target
Endurance at max load 60–200 h → 1,200 h all three test units completed
Brush life in service 4,000+ h average, replaced at scheduled maintenance

A true story, told from memory and anonymised. Any criticism is aimed at the systems — processes, interfaces and organisational habits of the time — never at the people working within them. Everyone involved was highly capable and doing their best inside structures that made the problem hard to see. That is rather the point.

Looking back, this was a Development Assurance story: assumptions and requirements not fully validated, an integration not fully verified, and changes nobody assessed. Development Assurance makes good integration a matter of process, not of competences we assume engineers have but never hold them to.

Bad supplier, you say…

Everyone knew whose fault it was.

The Thermal Management System (TMS) had underperformed since day one, and was getting less reliable every year. The supplier was already on the naughty list. Management had lost confidence in this ‘bad’ supplier, and the engineers tracking in-service reliability had reached much the same conclusion. Two years of investigation had produced plenty of blame and no improvement. A replacement supplier was being lined up.

The case against the supplier:

  • TMS performance: below 80% of the intended target since day one. Accepted, but always disappointing.
  • Component reliability: a brushed DC motor, part of a larger assembly, initially dependable. Its reliability had fallen fourfold over ten years. Some motors lasted only hundreds of hours.

Then came a dramatic in-service failure, in front of an important customer. It was the final straw.

Don’t assume anything

There were two problems to investigate: system-level performance, and the reliability of a sub-assembly component. Changing supplier would take an optimistic two years. The reliability issue had just become urgent, and writing the supplier off as ‘bad’ wasn’t going to solve it.

Performance

Before the dramatic incident, I had already started looking into the TMS performance. The supplier’s components all met their specification at the documented installation conditions. But the actual installed conditions did not match the specification given to the supplier, so installed performance fell below target, likely contributing to the ~20% system shortfall. As the component met its specification, only installation effects could explain it.

Unit-level verification had been done at the supplier. Installed unit performance had never been tested, to validate assumptions and verify the integration. The full system test had been done, the performance quantified, and the supplier blamed. It had been assumed that installing the supplier’s system had no effect on its performance.

Root cause · contributing

Uninvestigated component installation losses, outside the supplier’s control, were impacting system-level performance. The sole contributor? We will never know…

The seeds of doubt about the ‘bad supplier’ narrative had already been planted when I was asked to look into the now-urgent reliability issue.

Reliability

The first stop for any in-service degradation story is design change history. Two years had been spent investigating the supplier’s assembly, yet I could find no record of a design change to it since entry into service. The supplier confirmed the same, and I chose to trust them. So the next question was straightforward: what had changed around it?

Change the axis. Change the investigation.

The reliability data arrived plotted against calendar time: a gradual decline over several years. That showed when reliability had deteriorated. It did nothing to explain why.

Plotted by host installation serial number, it told a different story. The gradual decline became two distinct steps, each marked by a change in the installed environment configuration. At each one, reliability roughly halved.

Chart of motor reliability. Plotted against calendar time (blue) it declines gradually. Plotted against installation serial number (orange) it falls in two steps: when the circuit breaker was uprated, and when control changed from manual to automatic.
Figure 1 · Motor reliability degradation, by calendar time (blue) and by installation serial number (orange). Illustrative only; not from real data.

Two changes had been made:

  1. The motor circuit breaker had been uprated, following nuisance trips on some installations. The larger breaker stopped the trips, but if there had been an investigation into the trips themselves, there was no record of it.
  2. Automatic control had replaced manual control as part of a prior model upgrade. There was no record of an impact assessment on the TMS.

Both changes addressed an immediate operational concern. Their effects on motor life had not been adequately assessed.

Root causes · contributing

The uprated breaker allowed the motor to draw more current, working harder before tripping. Automatic control increased the rate of on/off cycling, known to accelerate wear. Other root causes: tbd…

The supplier still had a problem

None of this cleared the supplier of responsibility. The changes were staying. Motors were still burning out, and customers were demanding an urgent solution. I joined an expedition to the supplier to support the investigation.

We chose to be open with them about the installation changes, but firm about their responsibility. In my experience, ‘bad’ suppliers tend to exploit these situations. Thankfully these guys didn’t.

The supplier had run several endurance tests over two years. Under high load, motors lasted between 60 and 200 hours. Tinkering with higher-temperature-tolerant brush materials had proved fruitless.

In discussion it emerged that temperature sensors had been fitted to all four brushes during every test. The measurements existed, but nobody had explored their diagnostic value. I took the data back to the hotel that evening and was rewarded with another eureka moment. Across all the tests, the same two brushes consistently ran hotter than the rest. All of them were running hotter than the specification allowed.

Sometimes data is more valuable for the questions it raises:

  • Why were these particular brushes running hotter?
  • And a second, less comfortable one: even if all four brushes ran as cool as the coolest two, they would still be out of spec. The cooling provision itself was inadequate.

The dramatic failure hadn’t come from nowhere. The customers suffering most were operating long hours in hot climates — the conditions that consumed thermal margin fastest. Nobody had asked why some motors died in hundreds of hours while others lasted thousands. As with the installation, the supplier’s design hadn’t been fully validated.

Root cause · contributing

The assembly’s motor cooling provision was insufficient to meet the brush temperature specification over the full operating envelope.

The answer was in the lab

The following day, the supplier’s lab investigated while we met the supplier’s leadership, who were pushing a full system-wide upgrade. That was never going to fly. With their reputation where it was, our management wouldn’t wait 12–18 months for a redesign when a supplier switch would take them out of the picture altogether. I remained hopeful for a speedier solution.

The lab manager — whose methodical approach had impressed me the day before — interrupted the meeting. He had found two contributing problems:

  • A supporting bracket was obstructing airflow into the motor’s upper cooling inlets, the location of the two hotter brushes.
  • The hub of the fan at one end of the motor was the same diameter as the motor body, and was not drawing sufficient air through the motor.

He had already confirmed that removing the bracket reduced the temperature of the hot brushes. That afternoon, an off-the-shelf fan with a smaller hub (an important detail) was shown to reduce temperatures across all four.

The capability was there all along. What was missing was the connection between the data and the questions. The measurements had been waiting for two years, and an obvious question with them. Once that question had been asked, the problem almost solved itself.

Not done yet

The corrective action was to:

  • Improve airflow to the top of the motor, for more balanced brush cooling.
  • Change the fan blade for one that pulled air through the motor as well as over it.
Assembly conceptual schematic, before and after modification. Before: the frame obstructs the cooling inlet and a large fan hub restricts airflow through the motor. After: a cutout is added to the frame and a smaller hub increases airflow through the motor.
Figure 2 · Assembly design changes, before and after.

Testing showed that the two combined brought brush operating temperatures at maximum load into spec. We agreed a plan to introduce a design change to production, and a modification kit for in-service assemblies.

However, lower temperatures alone did not establish an acceptable service life. We insisted on three parallel endurance tests. The supplier resisted. But evidence was needed:

  • To demonstrate repeatable improvement under representative conditions.
  • To quantify the brush replacement interval and align it with scheduled maintenance.

The tests ran continuously for about two months — roughly the time needed to complete the design change approval, thanks to the off-the-shelf fan blade, which was already in service on a similar installation (it would have taken closer to six months otherwise). All three units completed 1,200 hours at maximum load, compared with the previous failures at 60–200 hours.

Before the modification, burnt-out brushes caused enough damage to write off the motor and be treated as a failure. Afterwards, brush wear could be managed through a service action: simply replacing the brushes. In service, average brush life subsequently exceeded 4,000 hours. Brush inspection and replacement was included in an existing scheduled maintenance action. As expected wear rather than failure, it no longer counted against reliability metrics. The improvement went beyond extending life: a destructive failure had been turned into manageable wear.

The investigation had connected in-service failure data, installed environment configuration, equipment design, test evidence and maintenance planning. There were important institutional lessons for both parties.

What happened next

Within months, the same supplier won the contract to introduce a new system as part of a wider model upgrade. Their proposal replaced all components within an updated architecture, alongside installation changes to meet the originally claimed specification. We got close but hit physical constraints, so we updated the specification accordingly, keeping documentation in line with implementation.

Two years from the start of the investigation, the upgraded system entered service, increasing TMS performance to 110% of the target value, even with the physical constraints. In time its components would achieve reliability far exceeding the strict contractual commitments introduced as a condition of winning the project.

It seemed the supplier wasn’t so bad after all.

And the alternative supplier, the one waiting in the wings? It had been developing the system for a new vehicle model in parallel with this investigation. A few years into service, that system was causing similar problems. Its supplier topped the naughty list, and the integration team was struggling with their ‘bad’ supplier. Similar integration and Development Assurance failings were later found, echoing the story above — the subject of future case studies.

Different supplier, same integration errors repeated. The devil hadn’t moved.

Organisational learning points

  1. Judge suppliers on evidence, then work with them. Use objective data, not anecdote. Both parties are fallible: trust their expertise and support their gaps.
  2. Validate assumptions across the full operating envelope. This covers installation conditions, climate and usage profile, documented on both sides. When suppliers challenge requirements, treat it as validation. Verify installed performance, not just unit compliance.
  3. Find root causes, plural.
    • Unit failures are often integration errors. If the unit hasn’t changed, look at what has.
    • Slice the data more than one way (time, configuration, operator), and ask why some units fail far sooner.
    • Protection trips are warnings, not nuisances.
    • Keep tracking known and unknown contributors; there is rarely a single cause.
  4. Interrogate test data. Capture it with diagnosis in mind. Expect to find questions, not just answers. Out-of-spec readings are findings, not background noise.
  5. Demand/Provide* change impact evidence for every change, on both sides. Cover performance, reliability (multiple endurance tests and service tracking), and production and maintenance impact.

* ‘Demand’ means the organisation should have a process in place to ensure this. ‘Provide’ places the responsibility on individuals where no such process exists.

Conclusion

The investigation began to move when we stopped treating “bad supplier” as a sufficient explanation and examined the complete system: its installation, configuration changes and physical failure mechanisms, relying on objective over anecdotal evidence.

No supplier is perfect, but few are wholly to blame. Development Assurance processes help to avoid costly mistakes at all levels of development, from cradle to grave. That is the Systems Engineering contribution: making connections, bringing the right people into the investigation, and carrying what we learnt through to a verified implementation of a validated design change.

Supplier management includes setting expectations and holding suppliers accountable. It also includes recognising where they need support — and where our own organisation is contributing to the failure.

After an experience like this, ask the questions:

What have we learned?
How would we act differently next time?
And, most importantly: how do we absorb this learning into the organisation?

Recognise this pattern in your own programme? Let’s talk, or read the other case studies.